What characterizes a sequential schedule?

Prepare for the Seattle Planning and Scheduling Professional Exam. Practice with engaging flashcards and multiple-choice questions, each with hints and explanations. Ensure your readiness for success!

A sequential schedule is characterized by tasks being performed one after another. This means that each task must be completed before the next one begins. In this type of scheduling, the completion of one task is dependent on the completion of the previous task, leading to a clear and organized flow of activities. This approach is often used in situations where specific prerequisites must be fulfilled before moving on to subsequent tasks, thereby minimizing risks and ensuring that each step in a process is adequately completed before the next one is initiated.

Choosing this option succinctly captures the essence of sequential scheduling, which prioritizes order and dependency among tasks to achieve a systematic outcome.