What distinguishes a fixed duration activity from a variable duration activity?

Prepare for the Seattle Planning and Scheduling Professional Exam. Practice with engaging flashcards and multiple-choice questions, each with hints and explanations. Ensure your readiness for success!

A fixed duration activity is characterized by having a predetermined time frame for its completion, meaning that the duration does not change regardless of the circumstances surrounding the project. This duration is typically established during the planning phase and remains constant throughout the life of the project. In contrast, a variable duration activity is influenced by various factors such as available resources, constraints in the project environment, and scheduling changes. This means the time taken to complete a variable activity can fluctuate based on these factors, reflecting more fluidity in project management.

Understanding this distinction is crucial for effective planning and scheduling because project managers must be able to identify which activities are fixed to allocate resources effectively and plan their timelines accurately. This knowledge also helps in assessing risk, as variable duration activities may lead to uncertainties that need to be mitigated throughout the project lifecycle.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy