When should a schedule change request typically be submitted?

Prepare for the Seattle Planning and Scheduling Professional Exam. Practice with engaging flashcards and multiple-choice questions, each with hints and explanations. Ensure your readiness for success!

A schedule change request should typically be submitted when there are changes in scope or unforeseen issues because these factors can significantly impact the overall project timeline. Changes in scope may arise from client requests, regulatory changes, or opportunities to improve project outcomes, necessitating adjustments to the schedule to accommodate new tasks or resources. Similarly, unforeseen issues, such as delays due to weather, unforeseen site conditions, or disruptions in supply chains, require promptly addressing to mitigate their impact on the project's progress and deliverables.

By submitting a schedule change request at this time, project managers can ensure that all stakeholders are aware of the modifications, align resources accordingly, and adjust plans to maintain project objectives. This proactive approach helps in managing expectations and can facilitate better decision-making regarding the project's future direction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy